Regulation 5 - Surveys
1 Every ship of 400 gross tonnage and above and every fixed and floating
drilling rig or other platform shall, to ensure compliance with the requirements of
chapter 3 of this Annex, be subject to the surveys specified below:
-
.1 An initial survey before the ship is put into service or before the
certificate required under regulation 6 of this Annex is issued for the first time.
This survey shall be such as to ensure that the equipment, systems, fittings,
arrangements and material fully comply with the applicable requirements of chapter 3 of this Annex;
-
.2 A renewal survey at intervals specified by the Administration, but
not exceeding five years, except where regulation 9.2,
9.5, 9.6 or 9.7 of this Annex is applicable. The renewal survey shall be
such as to ensure that the equipment, systems, fittings, arrangements and material
fully comply with applicable requirements of chapter 3 of this Annex;
-
.3 An intermediate survey within three months before or after the
second anniversary date or within three months before or after the third
anniversary date of the certificate which shall take the place of one of the
annual surveys specified in paragraph 1.4 of this regulation. The intermediate
survey shall be such as to ensure that the equipment and arrangements fully comply
with the applicable requirements of chapter 3 of this Annex and are in good working order. Such
intermediate surveys shall be endorsed on the IAPP Certificate issued under regulation
6 or 7 of this Annex;
-
.4 An annual survey within three months before or after each
anniversary date of the certificate, including a general inspection of the
equipment, systems, fittings, arrangements and material referred to in paragraph
1.1 of this regulation to ensure that they have been maintained in accordance with
paragraph 5 of this regulation and that they remain satisfactory for the service
for which the ship is intended. Such annual surveys shall be endorsed on the IAPP
Certificate issued under regulation 6 or 7 of this
Annex; and
-
.5 An additional survey either general or partial, according to the
circumstances, shall be made whenever any important repairs or renewals are made
as prescribed in paragraph 5 of this regulation or after a repair resulting from
investigations prescribed in paragraph 6 of this regulation. The survey shall be
such as to ensure that the necessary repairs or renewals have been effectively
made, that the material and workmanship of such repairs or renewals are in all
respects satisfactory and that the ship complies in all respects with the
requirements of chapter 3 of this Annex.
2 In the case of ships of less than 400 gross tonnage, the Administration
may establish appropriate measures in order to ensure that the applicable provisions of
chapter 3 of this Annex are complied with.
3 Surveys of ships as regards the enforcement of the provisions of this
Annex shall be carried out by officers of the Administration.
-
.1 The Administration may, however, entrust the surveys either to
surveyors nominated for the purpose or to organizations recognized by it. Such
organizations shall comply with the guidelines adopted by the Organization;footnote
-
.2 The survey of marine diesel engines and equipment for compliance
with regulation 13 of this Annex shall be conducted in
accordance with the revised NOX Technical Code 2008;
-
.3 When a nominated surveyor or recognized organization determines
that the condition of the equipment does not correspond substantially with the
particulars of the certificate, it shall ensure that corrective action is taken
and shall in due course notify the Administration. If such corrective action is
not taken, the certificate shall be withdrawn by the Administration. If the ship
is in a port of another Party, the appropriate authorities of the port State shall
also be notified immediately. When an officer of the Administration, a nominated
surveyor or recognized organization has notified the appropriate authorities of
the port State, the Government of the port State concerned shall give such
officer, surveyor or organization any necessary assistance to carry out their
obligations under this regulation; and
-
.4 In every case, the Administration concerned shall fully guarantee
the completeness and efficiency of the survey and shall undertake to ensure the
necessary arrangements to satisfy this obligation.
4 Ships to which chapter
4 of this Annex applies shall also be subject to the surveys specified below,
taking into account the guidelines adopted by the Organization:footnote
-
.1 An initial survey carried out before a new ship is put in service
and before the International Energy Efficiency Certificate is issued. The survey
shall verify that the ship’s attained EEDI is in accordance with the requirements
in chapter 4 of this Annex, and that the SEEMP required by
regulation
26 of this Annex is on board;
-
.2 A general or partial survey, according to the circumstances,
carried out after a major conversion of a new ship to which this regulation
applies. The survey shall ensure that the attained EEDI is recalculated as
necessary and meets the requirement of regulation
24 of this Annex, with the reduction factor applicable to the ship type
and size of the converted ship in the phase corresponding to the date of contract
or keel laying or delivery determined for the original ship in accordance with
regulation 2.2.18 of this Annex;
-
.3 In cases where the major conversion of a new or existing ship is so
extensive that the ship is regarded by the Administration as a newly constructed
ship, the Administration shall determine the necessity of an initial survey on
attained EEDI. Such a survey, if determined necessary, shall ensure that the
attained EEDI is calculated and meets the requirement of regulation
24 of this Annex, with the reduction factor applicable corresponding to
the ship type and size of the converted ship at the date of the contract of the
conversion, or in the absence of a contract, the commencement date of the
conversion. The survey shall also verify that the SEEMP required by regulation
26 of this Annex is on board and, for a ship to which regulation
27 applies, has been revised appropriately to reflect a major conversion
in those cases where the major conversion affects data collection methodology
and/or reporting processes;
-
.4 For existing ships, the verification of the requirement to have a
SEEMP on board according to regulation 26 of this Annex shall take place at the first
intermediate or renewal survey identified in paragraph 1 of this regulation,
whichever is the first, on or after 1 January 2013;
-
.5 The Administration shall ensure that for each ship to which regulation
27 applies, the SEEMP complies with regulation
26.2 of this Annex. This shall be done prior to collecting data under
regulation
27 of this Annex in order to ensure the methodology and processes are in
place prior to the beginning of the ship’s first reporting period. Confirmation of
compliance shall be provided to and retained on board the ship;
-
.6 The Administration shall ensure that, for each ship to which
regulation 28 applies, the SEEMP complies with regulation
26.3.1 of this Annex. This shall be done prior to 1 January 2023.
Confirmation of compliance shall be provided to, and retained on board, the ship;
-
.7 The verification that the ship's attained EEXI is in accordance
with the requirements in regulations 23 and 25 of this
Annex shall take place at the first annual, intermediate or renewal survey
identified in paragraph 1 of this regulation or the initial survey identified in
paragraphs 4.1 and 4.3 of this regulation, whichever is the first, on or after 1
January 2023; and
-
.8 Notwithstanding paragraph 4.7 of this regulation, a general or
partial survey, according to the circumstances, carried out after a major
conversion of a ship to which regulations
23 of this Annex applies. The survey shall ensure that the attained EEXI
is recalculated as necessary and meets the requirement of regulation
25 of this Annex.
5 The equipment shall be maintained to conform with the provisions of this
Annex and no changes shall be made in the equipment, systems, fittings, arrangements or
material covered by the survey, without the express approval of the Administration. The
direct replacement of such equipment and fittings with equipment and fittings that
conform with the provisions of this Annex is permitted.
6 Whenever an accident occurs to a ship or a defect is discovered that
substantially affects the efficiency or completeness of its equipment covered by this
Annex, the master or owner of the ship shall report at the earliest opportunity to the
Administration, a nominated surveyor or recognized organization responsible for issuing
the relevant certificate.
|
Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
|
|