2.1 The linings, ceilings and constructions should
be evaluated in accordance with this part using the arrangements described
below.
2.2 The ceilings should be tested in accordance
with paragraph 2.8 of the appendix 1 except that the ceiling should
be mounted on the horizontal furnace so that at least 150 mm high
"B" class bulkheads are mounted on the furnace and the ceiling is
fixed to these partial bulkheads by using the joining method as is
intended to be used in practice. Such ceilings and the joining methods
should be evaluated as required for ceilings in accordance with appendix
1 of this part and accordingly they should be classified as "continuous
'B' ("B-0" or "B-15", as applicable) class ceilings".
2.3 A lining which has been evaluated in accordance
with this part to be a "B" ("B-0" or "B-15", as applicable on basis
of the lining test) class lining may be considered as forming a "continuous
'B' ("B-0" or "B-15", as applicable) class lining" in conjunction
with a "continuous 'B' ("B-0" or "B-15", as applicable) class ceiling"
and with the joining method used in the test (see paragraph 2.2 above)
without further testing the lining.
2.4 An enclosed construction installed on an "A"
class deck and formed by "continuous 'B' ("B-0" or "B-15", as applicable)
class linings" and "continuous 'B' ("B-0" or "B-15", as applicable)
class ceiling" should be considered as forming a "continuous 'B' class
construction"