Section
6 Mooring arrangements
6.1 Mooring lines
6.1.3 It is recommended that not less than four mooring lines be carried on ships
exceeding 90 m in length, and not less than six mooring lines on ships exceeding 180 m
in length. The length of mooring lines should be not less than 200 m, or the length of
the ship, whichever is the lesser.
6.1.4 For ease of handling, fibre ropes should be not less than 20 mm diameter.
All ropes having breaking strengths in excess of 736,0 kN and used in normal mooring
operations are to be handled by, and stored on, suitably designed winches. Alternative
methods of storing should give due consideration to the difficulties experienced in
manually handling ropes having breaking strengths in excess of 490,0 kN
6.1.5 It is permitted to reduce the specified length of an individual mooring
line by up to 7 per cent, provided the total length of mooring lines is not less than
the total length if all the required lines were of equal given lengths. Proposals to fit
individual mooring lines of reduced length to suit the particular service will be
specially considered.
6.1.6 Ship Design Minimum Breaking Load (MBLSD) is the minimum breaking load
of new, dry mooring lines for which shipboard fittings and supporting hull structures
are designed in order to meet mooring restraint requirements.
6.1.7 Line Design Break Force (LDBF) is the minimum force at which a new, dry, spliced,
mooring line will break at. This is applicable to all synthetic cordage materials.
6.2 Mooring lines (Equipment Number ≤
2000)
6.2.1 It is recommended that the ship design minimum breaking load, length and
number of mooring lines provided on board ships with equipment number of less than
or equal to 2000 be not less than those specified in Table 5.6.1 Equipment - Kedge anchors and
wires, towlines and mooring lines. The equipment number is to be
calculated in accordance with Vol 1, Pt 3, Ch 5, 2.1 Equipment Number calculation. It is the Owner and designer's responsibility to ensure the
adequacy of the mooring equipment. The adequacy of minimum recommended mooring lines
in this sub-s ection needs to be verified based on assessments carried out for the
individual mooring arrangement, expected shore-side mooring facilities and design
environmental conditions for the berth.
6.2.3 As an alternative to the minimum recommendations for mooring lines prescribed in this
sub-section, the minimum recommendations for mooring lines may be determined by
direct mooring analysis in accordance with the procedure given in Appendix A of IACS
Recommendation 10 Chain Anchoring, Mooring and Towing Equipment.
6.3 Mooring lines (Equipment Number > 2000)
6.3.1 It is recommended that the ship design minimum breaking load, length and
number of mooring lines for ships with an equipment number greater than 2000 are as
defined in this sub-Section. The equipment number is to be calculated in accordance
with Vol 1, Pt 3, Ch 5, 2.1 Equipment Number calculation. It is the Owner and designer’s responsibility to ensure the
adequacy of the mooring equipment. The adequacy of minimum recommended mooring lines
in this sub-section needs to be verified based on assessments carried out for the
individual mooring arrangement, expected shore-side mooring facilities and design
environmental conditions for the berth. A typical mooring arrangement is indicated
in Figure 5.6.1 Typical mooring arrangement and the following is defined with respect to mooring lines.
- Breast line: A mooring line that is deployed
perpendicular to the ship, restraining the ship in the off-berth direction.
- Spring line: A mooring line that is deployed almost
parallel to the ship, restraining the ship in the fore or aft direction.
- Head/stern line: A mooring line that is oriented between
longitudinal and transverse direction, restraining the ship in the off-berth
and in the fore or aft direction. The amount of restraint in fore or aft and
off-berth direction depends on the line angle relative to these directions.
6.3.2 The strength of mooring lines and the number of head, stern, and breast
lines for ships with an Equipment Number > 2000 is based on the side-projected
area A1. Side-projected area A1 is to be
calculated similar to the side-projected area A, according to Vol 1, Pt 3, Ch 5, 2.1 Equipment Number calculation but considering the following conditions:
- For ships with substantial variation in draught such as
fleet tankers, the ballast draught is to be considered for the calculation
of the side-projected area A1. For ship types having small
variation in the draught, the side projected area A1 may
be calculated using the design draught waterline.
- Wind shielding of the pier can be considered for the
calculation of the side-projected area A1 unless the ship
is intended to be regularly moored to jetty type piers. The lower part of
the side projected area above the waterline for the considered loading
condition can be disregarded up to the pier height in the calculation of the
side-projected area A1. Where known, the actual height of
the pier above the waterline may be used in the calculation. If the pier
height cannot be pre-determined, an assumed height may be used. However, in
both cases, the pier height shall not exceed 3 m.
6.3.3 The mooring lines specified are based on a maximum current speed of 1,0
m/s and the following maximum wind speed Vw :
Vw |
= |
25,0 − 0,002 (A1 – 2000) m/s for ships with large side
projected area, i.e. 2000 m2 < A1 ≤ 4000
m2 |
= |
21,0 m/s for ships with large side projected area A1 >
4000 m2 |
= |
25,0 m/s for other ships |
6.3.4 The maximum wind speed Vw is representative of the
mean wind speed over a 30 second period from any direction and at a height of 10 m
above the ground. The current speed considered is a representative of the maximum
current speed acting on bow or stern (±10°) at a depth of one-half of the mean
draught. Furthermore, it is considered that the ships are moored to solid piers that
provide shielding against cross currents.
6.3.5 Additional loads caused by higher wind or current speeds, cross currents, additional
wave loads, or reduced shielding from non-solid piers, for example are to be
specially considered. Consideration is also to be given to the fact that
unfavourable mooring layouts can significantly increase the loads on individual
mooring lines.
Figure 5.6.1 Typical mooring arrangement
6.3.6 The ship design minimum breaking load ( MBLSD), in kN,
of the mooring lines is to be taken as:
MBLSD |
= |
|
6.3.7 The ship design minimum breaking load may be limited to 1275 kN (130
tonnes). However in these cases, the moorings are to be considered as not sufficient
for the environmental conditions given by Vol 1, Pt 3, Ch 5, 6.3 Mooring lines (Equipment Number > 2000) 6.3.3. For these ships, the acceptable wind speed
, in m/s, to be calculated as
follows:
However, the intended ship design minimum breaking load
is not to be taken less than that corresponding to
an acceptable wind speed of 21 m/s:
6.3.9 The total number of head, stern and breast lines is specified as:
n |
= |
|
The total number of head, stern and breast lines is to be rounded to the
nearest whole number. The number may be increased or decreased in conjunction with
an adjustment to the ship design minimum breaking load. The adjusted ship design
minimum breaking load , is to be taken as:
Vice versa, the ship design minimum breaking load of head, stern and
breast lines may be increased or decreased in conjunction with an adjustment to the
number of lines.
6.3.10 The total number of spring lines, ns is to be taken
not less than:
- Two lines where EN < 5000,
- Four lines where EN ≥ 5000.
The ship design minimum breaking load of spring lines is to be the same
as that of the head, stern and breast lines. If then the number of head, stern and
breast lines is increased in conjunction with an adjustment to the ship design
minimum breaking load of the lines, the number of spring lines is to be taken as
follows, but rounded up to the nearest even number.
where
MBLSD |
= |
MBLSD or , if the intended ship design minimum
breaking load is different as provided by Vol 1, Pt 3, Ch 5, 6.3 Mooring lines (Equipment Number > 2000) 6.3.7 or Vol 1, Pt 3, Ch 5, 6.3 Mooring lines (Equipment Number > 2000) 6.3.8 |
|
= |
adjusted ship design minimum breaking load as provided by Vol 1, Pt 3, Ch 5, 6.3 Mooring lines (Equipment Number > 2000) 6.3.9 |
ns |
= |
the number of spring lines as given above |
|
= |
the increased number of spring lines |
6.3.11 As an alternative to the minimum recommendations for mooring lines prescribed in this
sub-section, the minimum recommendations for mooring lines may be determined by
direct mooring analysis in accordance with the procedure given in Appendix A of IACS
Recommendation 10 ‘Chain Anchoring, Mooring and Towing Equipment’.
Table 5.6.1 Equipment - Kedge anchors and
wires, towlines and mooring lines
Equipment
number
|
Equipment Letter
|
|
|
Mooring lines (see
Notes 2 and 5)
|
Mass of stockless kedge anchor, in kg
|
Kedge anchor wire or chain (see
Notes 1 and 2)
|
Exceeding
|
Not exceeding
|
|
Minimum length, in metres
|
Minimum breaking strength, in kN
|
Number
|
Minimum length of each line, in metres
|
ship design minimum breaking load (MBLSD), in
kN
|
50
|
70
|
A
|
68
|
110
|
46
|
3
|
80
|
37
|
70
|
90
|
B
|
90
|
110
|
58
|
3
|
100
|
40
|
90
|
110
|
C
|
113
|
124
|
75
|
3
|
110
|
42
|
110
|
130
|
D
|
135
|
124
|
90
|
3
|
110
|
48
|
130
|
150
|
E
|
158
|
138
|
90
|
3
|
120
|
53
|
150
|
175
|
F
|
180
|
138
|
122
|
3
|
120
|
59
|
175
|
205
|
G
|
214
|
151
|
106
|
3
|
120
|
64
|
205
|
240
|
H
|
248
|
151
|
140
|
4
|
120
|
69
|
240
|
280
|
I
|
292
|
165
|
166
|
4
|
120
|
75
|
280
|
320
|
J
|
338
|
179
|
195
|
4
|
140
|
80
|
320
|
360
|
K
|
383
|
179
|
225
|
4
|
140
|
85
|
360
|
400
|
L
|
428
|
193
|
257
|
4
|
140
|
96
|
400
|
450
|
M
|
484
|
193
|
292
|
4
|
140
|
107
|
450
|
500
|
N
|
540
|
206
|
328
|
4
|
140
|
117
|
500
|
550
|
O
|
597
|
206
|
328
|
4
|
160
|
134
|
550
|
600
|
P
|
653
|
220
|
366
|
4
|
160
|
143
|
600
|
660
|
Q
|
720
|
220
|
406
|
4
|
160
|
160
|
660
|
720
|
R
|
788
|
220
|
448
|
4
|
160
|
171
|
720
|
780
|
S
|
855
|
233
|
491
|
4
|
170
|
187
|
780
|
840
|
T
|
923
|
233
|
540
|
4
|
170
|
202
|
840
|
910
|
U
|
990
|
233
|
585
|
4
|
170
|
218
|
910
|
980
|
V
|
1069
|
248
|
635
|
4
|
170
|
235
|
980
|
1060
|
W
|
1148
|
248
|
685
|
4
|
180
|
250
|
1060
|
1140
|
X
|
1238
|
248
|
685
|
4
|
180
|
272
|
1140
|
1220
|
Y
|
1328
|
261
|
740
|
4
|
180
|
293
|
1220
|
1300
|
Z
|
1418
|
261
|
795
|
4
|
180
|
309
|
1300
|
1390
|
A†
|
1519
|
261
|
855
|
4
|
180
|
336
|
1390
|
1480
|
B†
|
1620
|
275
|
905
|
4
|
180
|
352
|
1480
|
1570
|
C†
|
1721
|
275
|
970
|
5
|
190
|
352
|
1570
|
1670
|
D†
|
1834
|
275
|
1030
|
5
|
190
|
362
|
1670
|
1790
|
E†
|
1969
|
289
|
1095
|
5
|
190
|
384
|
1790
|
1930
|
F†
|
2104
|
289
|
1155
|
5
|
190
|
411
|
1930
|
2080(5)
|
G†
|
2250
|
289
|
1225
|
5
|
190
|
437
|
2080
|
2230
|
H†
|
2419
|
302
|
1290
|
|
|
|
2230
|
2380
|
I†
|
2588
|
302
|
1395
|
|
|
|
2380
|
2530
|
J†
|
2759
|
302
|
1505
|
|
|
|
2530
|
2700
|
K†
|
2925
|
316
|
1580
|
|
|
|
2700
|
2870
|
L†
|
3113
|
316
|
1690
|
|
|
|
2870
|
3040
|
M†
|
3263
|
316
|
1805
|
|
|
|
3040
|
3210
|
N†
|
3488
|
330
|
1805
|
|
|
|
3210
|
3400
|
O†
|
3713
|
330
|
1925
|
|
|
|
3400
|
3600
|
P†
|
3938
|
330
|
2045
|
|
|
|
3600
|
3800
|
Q†
|
4163
|
344
|
2130
|
|
|
|
3800
|
4000
|
R†
|
4388
|
344
|
2255
|
|
|
|
4000
|
4200
|
S†
|
4613
|
344
|
2340
|
|
|
|
Note 1. The rope
used for kedge anchor wire is to be constructed of not less than
72 wires, made up into six strands.
|
|
Note 3. Wire ropes
for mooring lines used in association with mooring winches (on
which the rope is stored on the winch drum) are to be of
suitable construction.
|
Note 4. Irrespective
of strength requirements, no fibre rope is to be less than 20 mm
diameter.
|
Note 5. The mooring
lines to be selected only for ships with equipment number less
than or equal to 2000.
|
6.4 Materials
6.4.1 Mooring
lines may be of steel wire rope, natural fibre or synthetic fibre.
The diameter, construction and specification of wire or natural fibre
mooring lines are to comply with the requirements of Ch 10 Equipment for Mooring and Anchoring of the Rules for Materials. Where
it is proposed to use synthetic fibre ropes, the size and construction
will be specially considered.
6.4.2 The design loads applied to deck fittings by Vol 1, Pt 3, Ch 5, 6.9 Deck fittings and support structure relate to conventional fibre ropes (i.e.
polypropylene, polyester and nylon). If other materials are used i.e. HMPE,
consideration should be given to the elongation properties and therefore the design load
applied to deck fittings.
6.4.3 Wire
rope mooring lines used in association with winches (on which the
rope is stored on the winch drum) are to be of suitable construction.
6.5 Testing and certification
6.6 Bollards, fairleads and bull rings
6.6.1 Means
are to be provided to enable mooring lines to be adequately secured
on board ship.
6.6.2 It is recommended that the total number of suitably placed bollards on
either side of the ship and/or the total brake holding power of mooring winches should
be capable of holding not less than 1,5 times the sum of the ship design minimum
breaking load (MBLSD) of the mooring lines recommended.
6.7 Mooring arrangement and winches
6.7.1 The recommendations with respect to the mooring arrangement and mooring winches are
provided by this sub-Section.
6.7.2 Mooring lines in the same service (e.g. breast lines) are to be of the same
characteristics in terms of strength and elasticity.
6.7.3 Mooring winches where provided are to be suitable for the intended purpose. As far as
possible, a sufficient number of mooring winches is to be fitted so as to allow all
mooring lines to be belayed on winches. This allows for an efficient distribution of
the load to all mooring lines in the same service and for the mooring lines to shed
the load before they break. If the mooring arrangement is designed such that mooring
lines are partly to be belayed on bitts or bollards, it is to be understood that
these lines may not be as effective as the mooring lines belayed on winches.
6.7.4 The mooring winch is to be fitted with brakes, the holding capacity of
which is sufficient to prevent unreeling of the mooring line when the rope tension
is equal to 80 per cent of the ship design minimum breaking load of the rope as
fitted on the first layer. The winch is to be fitted with brakes that will allow for
the reliable setting of the brake rendering load.
6.7.5 For powered winches the maximum hauling tension which can be applied to
the mooring line (the reeled first layer) is to be not less than 2/9, nor to be more
than, 1/3, of the rope's ship design minimum breaking load. For automatic winches
these figures apply when the winch is set to the maximum power with automatic
control.
6.7.6 For powered winches on automatic control, the rendering tension which the winch can
exert on the mooring line (the reeled first layer) is not to exceed 1,5 times, nor
be less than 1,05 times, the hauling tension for that particular power setting of
the winch. The winch is to be marked with the range of rope strengths for which it
is designed.
6.7.7 Mooring lines are to have a straight lead from the mooring drum to the fairlead as
far as practicable.
6.7.8 When a mooring line changes direction, the contact surface on the fitting shall have
a large radius so as to minimise the wear experienced by the mooring lines.
Recommendations from the rope manufacturer for the intended rope type are also to be
complied with.
6.8 Mooring line construction
6.8.1 Mooring lines are to be of wire, natural fibre or synthetic fibre construction or of
a mixture of wire and fibre. For synthetic fibre ropes it is recommended that lines
with reduced risk of recoil (snap-back) be used to mitigate the risk of injuries or
fatalities in the case mooring line failure.
6.8.2 Notwithstanding the strength recommendations, no fibre rope shall be
less than 20 mm in diameter. For polyamide ropes the line design break force is to
be increased by 20 per cent and for other synthetic ropes by 10 per cent to account
for strength loss due to, among other causes, aging and wear.
6.8.3 Wire ropes used for mooring lines are generally to be of a flexible construction with
not less than 144 wires in six strands with seven fibre cores for strengths up to
490 kN, and 222 wires in six strands with one fibre core for strengths exceeding 490
kN. The wires laid round the fibre centre of each strand are to be made up in not
less than two layers.
6.8.4 Wire ropes for mooring lines used in association with mooring winches (on which the
rope is stored on the winch drum) are to be of suitable construction.
6.9 Deck fittings and support structure
6.9.1 The strength of shipboard fittings used for mooring operations and their supporting
hull structures as well as the strength of supporting hull structures of winches and
capstans are to comply with the requirements specified in this sub-Section.
6.9.2 Shipboard fittings, winches and capstans for mooring are to be located on stiffeners
and/or girders which are part of the deck construction so as to facilitate efficient
distribution of the mooring load. Other arrangements are acceptable (for chocks in
bulwarks, etc.) provided that the strength is confirmed adequate for the service.
6.9.4 The design load is to be applied to fittings in all directions that may
occur by taking into account the arrangement shown on the towing and mooring
arrangements plan. Where the mooring line takes a turn at a fitting the total design
load applied to the fitting is equal to the resultant of the design loads acting on
the line, see
Figure 5.6.2 Design load applied to fittings.
However, in no case does the design load applied to the fitting need to be greater
than twice the design load on the line.
Figure 5.6.2 Design load applied to fittings
6.9.6 Mooring bitts (double bollards) are to be chosen for the mooring line
attached in figure-of-eight fashion if the industry standard distinguishes between
different methods to attach the line, i.e. figure-of-eight or eye-splice attachment.
With the line attached to a mooring bitt in the usual way (figure-of-eight fashion),
either of the two posts of the mooring bitt can be subjected to a force twice as
large as that acting on the mooring line. Disregarding this effect, depending on the
applied industry standard and fitting size, overload may occur.
6.9.7 When the shipboard fitting is not selected from an accepted industry
standard, the strength of the fitting based on net scantlings and its attachment to
the ship is to be adequate for the loads specified in Table 5.6.2 Minimum design load for deck
fittings and supporting structure - Mooring based on the acceptance
criteria given Vol 1, Pt 3, Ch 5, 6.9 Deck fittings and support structure 6.9.10 or Vol 1, Pt 3, Ch 5, 6.9 Deck fittings and support structure 6.9.11 as appropriate. Mooring bitts (double bollards) are
required to resist the loads caused by the mooring line attached in figure-of-eight
fashion. For strength assessment, beam theory or finite element analysis using net
scantlings is to be applied, as appropriate. Wear down allowance for shipboard
fittings not selected from an accepted industry standard is not to be less than 1,0
mm, added to surfaces which are intended to regularly contact the line.
Table 5.6.2 Minimum design load for deck
fittings and supporting structure - Mooring
Use/Item
|
Minimum design load (see Notes 1 to 2)
|
Mooring
(Fittings and its supporting hull
structure)
|
1,15 times the ship design minimum breaking load given in Vol 1, Pt 3, Ch 5, 6.1 Mooring lines 6.1.1 or Vol 1, Pt 3, Ch 5, 6.1 Mooring lines 6.1.2 as appropriate
|
Winches
(Supporting hull structure
only)
|
1,25 times the intended maximum brake holding load, where the
maximum brake holding load is to be assumed not less than 80% of the
ship design minimum breaking load given in Vol 1, Pt 3, Ch 5, 6.1 Mooring lines 6.1.1 or Vol 1, Pt 3, Ch 5, 6.1 Mooring lines 6.1.2 as appropriate
|
Capstans
(Supporting hull structure
only)
|
1,25 times the maximum hauling in force, where hauling in force is
defined as the maximum pull of the capstan or 1,25 times the
intended maximum brake holding load if that be greater
|
Note 2. The increase
of the line design break force for synthetic ropes need not to
be taken into account for the loads applied to shipboard
fittings and supporting hull structure.
|
6.9.9 For bollards and bitts the attachment point of the mooring line is to be
taken not less than 4/5 of the tube height above the base, see
Figure 5.6.3 Supporting hull
structure. However, if fins are fitted to the bollard tubes to keep the
mooring line as low as possible, then the attachment point of the mooring line is to
be taken at the location of the fins, see
Figure 5.6.3 Supporting hull
structure.
Figure 5.6.3 Supporting hull
structure
6.9.11 For strength assessment by means of finite element analysis the mesh is
to be fine enough to represent the geometry as realistically as possible. The aspect
ratios of elements are not to exceed three. Girders are to be modelled using shell
or plane stress elements. Symmetric girder flanges may be modelled by beam or truss
elements. The element height of girder webs must not exceed one-third of the web
height. In way of small openings in girder webs the web thickness is to be reduced
to an appropriate mean thickness over the web height. Large openings are to be
modelled. Stiffeners may be modelled using shell or plane stress elements. The mesh
size of stiffeners is to be fine enough to obtain proper bending stress. If flat
bars are modelled using shell or plane stress elements, then dummy rod elements are
to be modelled at the free edge of the flat bars and the stresses of the dummy
elements are to be evaluated. Stresses are to be read from the centre of the
individual element. For shell elements the stresses are to be evaluated at the mid
plane of the element. The Von Mises stress within the supporting structure of
fittings, calculated with net scantlings, is not to exceed the specified minimum
yield strength of the material.
6.9.13 The SWL, in tonnes, of each shipboard fitting is to be marked (by weld bead or
equivalent) on the deck fittings used for mooring.
6.9.14 The above requirements on SWL apply for the use with no more than one mooring line.
6.9.15 The mooring arrangements plan as mentioned in Vol 1, Pt 3, Ch 5, 6.10 Mooring arrangements plan is to
define the method of use of mooring lines.
Table 5.6.3 Allowable stress within the supporting structure of shipboard
fittings
|
Normal
stress, in N/mm2
|
Shear
stress, in N/mm2
|
Allowable
stress
|
|
|
where
σ0
= specified minimum yield strength of the material in
N/mm2
Note Normal stress is
defined as the sum of bending and axial stresses. No stress
concentration factors accounted for and as such may need to be
considered separately.
|
6.10 Mooring arrangements plan
6.10.1 The SWL for the intended use for each shipboard fitting is to be noted in the mooring
arrangements plan available on board for the guidance of the Master.
6.10.2 Information provided on the plan is to include in respect of each
shipboard fitting:
- location on the ship;
- fitting type;
- SWL;
- purpose, i.e. mooring; and
- manner of applying towing or mooring line load,
including limiting fleet angles, i.e. angle of change in direction of a line
at the fittings.
Note Item (c) with respect to
items (d) and (e), is subject to approval.
Furthermore, information provided on the plan is to include:
- the arrangement of mooring lines showing number of lines
(N);
- the ship design minimum breaking load
(MBLSD, MBLSD* or
MBLSD** as appropriate); and
- the acceptable environmental conditions, the minimum
environmental conditions are as given in Vol 1, Pt 3, Ch 5, 6.3 Mooring lines (Equipment Number > 2000) for the recommended ship design
minimum breaking load for ships with EN > 2000:
- 30 second mean wind speed from any direction
(Vw or )
- Maximum current speed acting on bow or stern
(±10°).
|