Section
7 Inspection and testing procedures
7.1 General
7.1.1 The test procedures detailed in this Section are to be used to confirm the
watertightness of tanks and watertight boundaries, the structural adequacy of tanks and
the weathertightness of structures.
7.1.2 A structural and leak test plan is to be submitted defining the compartments
or tanks to be tested and the method of testing in accordance with the requirements of
this Section.
7.1.3 Although referred to as watertight, some compartments or tanks may require
to be tested as gastight or oil-tight.
7.1.4 The testing requirements for gravity tanks, defined as tanks subject to a
vapour pressure not greater than 70 kN/m2, independent tanks and watertight
and weathertight compartments, are listed in Table 6.7.1 Testing
requirements. Tests are to be carried out in
the presence of the Surveyor at a stage sufficiently close to completion such that the
strength and tightness are not subsequently impaired by subsequent work and prior to any
sealing and cement work being applied over joints.
7.1.5 For naval vessels which are also required to comply with SOLAS, structural testing is to
be carried out for all tanks forming part of the watertight sub-division of the ship in
accordance with SOLAS requirements unless:
- the shipyard provides documentary evidence of the Owner’s
agreement to a request to the appropriate Naval or Flag Administration for an
exemption from the application of SOLAS Chapter II-1 Regulation 11 - Initial testing of watertight bulkheads, etc.,
or for an exemption agreeing that the proposed alternative approach is equivalent to
SOLAS Chapter II-1 Regulation 11 - Initial testing of watertight bulkheads, etc.;
and
- the above-mentioned exemption/equivalency has been granted by
the responsible Naval or Flag Administration.
7.1.6 The testing of structures not listed in this Section is to be specially considered.
7.2 Test types
7.2.1 The types of test specified in this Section are:
- Structural test, which is to be conducted to verify the
tightness and structural adequacy of the construction of tanks. This may be
a hydrostatic test or, where the situation warrants, a hydropneumatic test.
- Leak test, which is to be used to verify the tightness
of a boundary. Unless a specific test is indicated, this may be a
hydrostatic, hydropneumatic test, air or other medium test.
- Gastight test, which is to be used to verify the gas
tightness of a boundary using a pressure drop test.
Table 6.7.1 Testing
requirements
Item to be
tested
|
Testing
procedure
|
Installation testing
requirement
|
Double bottom tanks
|
Leak and structural
|
The greater of: (3)
— head of
water up to the top of the overflow
— head of water
representing the maximum pressure experienced in service for
which elastic design criteria were used.
— head of
water 2,4 m above top of tank for NS1 ships (3)
— head
of water 1,8 m above top of tank for NS2 and NS3 ships
(3)
|
Peak tanks (2)
|
Leak and structural
|
The greater of: (3)
— head of water
up to the top of the overflow
— head of water 2,4 m
above top of tank for NS1 ships (3)
— head of water
1,8 m above top of tank for NS2 and NS3 ships
(3)
|
Deep tanks
|
Leak and structural
|
The greater of: (3)
—
head of water up to the top of the overflow
— head of
water 2,4 m above top of tank for NS1 ships
— head of
water 1,8 m above top of tank for NS2 and NS3 ships
—
head of water up to top of tank, plus setting of fitted
pressure relief valves
|
Scupper and discharge pipes in way of
tanks
|
Leak and structural
|
Sea inlet boxes Sonar
spaces
|
Leak
|
See
Vol 1, Pt 6, Ch 6, 7.5 Leak testing
|
Speed and depth instrument
compartments
|
Structural (1)
|
See
Vol 1, Pt 6, Ch 6, 7.5 Leak testing
|
Double plate rudders blades and bilge
keels
|
Leak
|
See
Vol 1, Pt 6, Ch 6, 7.5 Leak testing
|
Watertight bulkheads, shaft funnels,
flats and recesses, etc.
|
Leak (4)
|
Vol 1, Pt 6, Ch 6, 7.5 Leak testing
|
Watertight doors, hatches and closing
appliances (below the vertical limit of watertight integrity)
when fitted in place
|
Leak (4), (5) and (9)
|
Shell doors when fitted in
place
|
Leak (4) and (6)
|
Weathertight hatch covers, doors and
closing appliances (above the vertical limit of watertight
integrity)
|
Leak (4)
|
Shaft tunnel clear of deep
tanks
|
Leak (4)
|
Cofferdams
|
Leak
|
Peak spaces with equipment
|
Leak
|
Peak voids
|
Leak
|
Chain locker
|
Leak and structural
|
Head of water up to the top of the
spurling pipe
|
Independent/separate fuel oil tanks
(11) Filing trunks
|
Leak and structural
|
Head of water equal to the maximum to
which the tanks/trunks may be subjected, but not less than 2,5 m
above the top of the tank/trunk. (3)
|
Magazines
|
Leak (8)
|
See
Vol 1, Pt 6, Ch 6, 7.5 Leak testing
|
Double bottom and double side voids
(1)
|
Leak
|
Vol 1, Pt 6, Ch 6, 7.5 Leak testing
|
LO sump tanks and other similar
tanks/spaces under main engines
|
Leak (10)
|
Vol 1, Pt 6, Ch 6, 7.5 Leak testing
|
Ballast ducts
|
Leak and structural
|
The greater of:
— ballast pump
maximum pressure
— setting of pressure relief
valve
|
|
Note
2. Testing of the after
peak is to be carried out after the sterntube has been
fitted.
|
Note
3. The top of the tank is
generally to exclude hatchways.
|
|
Note
5. Watertight doors and
hatches not confirmed watertight by a prototype test are
to be subject to a hydrostatic test.
|
Note
6. For shell doors
providing watertight closure, watertightness is to be
demonstrated through prototype testing before
installation. The testing procedure is to be agreed with
LR prior to testing.
|
|
Note
8. If the magazine is
required to contain an overpressure, for example due to
a fire munitions reaction, the testing requirements are
to be specified by the magazine safety standard. Where
magazines are not required to contain an overpressure,
or required to be watertight, leak testing may be
replaced by a visual examination.
|
Note
9. All watertight doors
and hatches are to be hose tested after installation.
Hose testing is to be carried out from each side of a
door unless, for a specific application, flooding is
anticipated from only one side. Where a hose test is not
practicable because of possible damage to machinery,
electrical equipment insulation or outfitting items, it
may be replaced by an ultrasonic leak test or an
equivalent test.
|
Note
10. Where LO sump tanks
and other similar spaces under main engines intended to
hold liquid form part of the watertight sub-division of
the ship, they are to be tested in accordance with the
requirements for deep tanks (other than those listed
elsewhere).
|
Note
11. Independent tanks not
confirmed watertight by a prototype test are to be
subject to a hydrostatic test. A leak test is to be
carried out after installation on board.
|
Note
12. Where hose testing
cannot be performed without damaging possible
outfittings already installed, it can be replaced by a
careful visual inspection of all the crossings and
welded joints. Where necessary, dye penetrant test or
ultrasonic leak test could be required.
|
7.3 Structural testing – general requirements
7.3.1 Tanks which are intended to hold liquids, and which form part of the watertight
sub-division of the ship, shall be tested for tightness and structural strength as
indicated in Table 6.7.1 Testing
requirements.
Tanks which do not form part of the watertight sub-division of the ship need not be
structurally tested providing that the watertightness of all boundaries of these
spaces is verified by leak tests and thorough inspection.
7.3.2 Where a structural test is specified in Table 6.7.1 Testing
requirements
unless specified otherwise, a hydrostatic test is to be carried out in accordance
with Vol 1, Pt 6, Ch 6, 7.7 Definitions and details of tests 7.7.1. Where practical limitations prevent a hydrostatic test
being carried out, a hydropneumatic test in accordance with Vol 1, Pt 6, Ch 6, 7.7 Definitions and details of tests 7.7.2 may be conducted. All external boundaries of the tested
space are to be examined for structural distortion, bulging, buckling, or other
related damage and/or leaks.
7.3.3 A hydrostatic test or hydropneumatic test can be carried out afloat to confirm the
structural adequacy of tanks, provided that a leak test is carried out and the
results are confirmed as satisfactory before the vessel is afloat. The testing
afloat is to be carried out by separately filling each tank and cofferdam to the
test head given in Table 6.7.1 Testing
requirements. An
internal inspection of the tanks is to be made whilst the ship is afloat.
7.3.4 Consideration is to be given to the selection of tanks to be structurally tested.
Selected tanks are to be chosen so that all representative structural members are
tested for the expected tension and compression. Tank boundaries are to be tested
from at least one side.
7.3.5 Compartments to be tested are to be structurally complete and all fittings which
affect the watertight integrity of the compartment such as doors, hatches, manholes,
penetrations, valves and glands are to be fitted.
7.3.6 In compartments containing the stabiliser fins, rudder stocks, sonar hull outfit,
echo sounders, etc. the bearing houses are to be installed and the seating
arrangements completed before testing.
7.3.7 Arrangements are to be provided to ensure the free passage of air from the top of the
tank tested. The air pipe or indicator test plug may be used for this purpose.
7.3.8 Where necessary, additional temporary supports are to be fitted to the hull to
prevent excessive deformation.
7.3.9 It is recommended that a leak test in accordance with Vol 1, Pt 6, Ch 6, 6.7 Watertight collars is carried out
before the structural test commences to identify any leak paths which may compromise
the structural test.
7.3.10 Where it is intended to carry out structural tests after the protective coating has
been applied, welds are to be leak tested prior to the coating application.
7.3.11 For welds other than manual and automatic erection welds, manual fillet welds on tank
boundaries and manual penetration welds, the leak test may be waived provided that
careful visual inspection is carried out, to the satisfaction of the Surveyor,
before the coating is applied. The cause of any discolouration or disturbance of the
coating during the test is to be ascertained, and any deficiencies repaired.
7.3.12 Equivalent proposals for testing will be considered.
7.3.13 Where it is intended to carry out structural tests after the protective coating has
been applied, welds are to be leak tested prior to the coating application.
7.4 Structural testing for Naval ships
7.4.1 For tanks of the same structural design, configuration and the same general
workmanship, as determined by the attending Surveyor, a structural test need only be
carried out on one tank, provided that all subsequent tanks are tested for leaks by
an air test.
7.4.2 Where the structural adequacy of a tank has been verified by structural testing on a
previous vessel in a series, tanks of structural similarity on subsequent vessels
within that series (which are built at the same shipyard) need not be structurally
tested, provided that the watertightness of all exempt tanks is verified by leak
tests and thorough inspection. However, structural testing is to be carried out for
at least one tank of each type of tank on every vessel in the series.
7.4.3 For sister ships built two or more years after the delivery of the last
ship of the series, the application of the provisions of Vol 1, Pt 6, Ch 6, 7.4 Structural testing for Naval ships 7.4.2 will be specially considered provided that the general practices,
equipment and workmanship of the shipyard have been maintained continuously, and an
non-destructive testing programme is implemented for the tanks not subject to
structural tests.
7.5 Leak testing
7.5.1 Generally all boundaries for watertight subdivision are to be given a leak
test when structural work is complete. The test is to be carried out before the
compartment is fitted out and linings or covering applied.
7.5.2 Testing is to be carried out by applying an efficient indicating liquid,
e.g. soapy water solution, to the weld or outfitting penetration being tested, while the
tank or compartment is subject to an air pressure of at least 0,15 bar.
7.5.3 It is recommended that the air pressure be raised to 0,2 bar and kept at
this level for about one hour to reach a stabilised state, with a minimum number of
personnel in the vicinity, and then lowered to the test pressure prior to inspection.
7.5.4 A U-tube filled with water to a height corresponding to the test pressure
is to be fitted for verification and to avoid over-pressure. The U-tube is to have a
cross-section larger than that of the air supply pipe. In addition, the test pressure is
to be verified by means of a calibrated pressure gauge, or alternative equivalent
system.
7.5.5 Leak testing is to be carried out, prior to the application of a protective
coating, on all fillet welds and erection welds on tank boundaries, except welds made by
automatic processes and on all outfitting penetrations.
7.5.6 Selected locations of automatic erection welds and pre-erection manual or
automatic welds may also be required to be tested before coating, at the discretion of
the Surveyor.
7.5.7 Where a leak test is specified in Table 6.7.1 Testing
requirements unless specified otherwise, a tank air test, compressed air
fillet weld test or vacuum box test is to be carried out in accordance with the
applicable requirements of Vol 1, Pt 6, Ch 6, 7.7 Definitions and details of tests 7.7.4 to Vol 1, Pt 6, Ch 6, 7.7 Definitions and details of tests 7.7.6. A hydrostatic or hydropneumatic test conducted in accordance
with the applicable requirements of Vol 1, Pt 6, Ch 6, 7.7 Definitions and details of tests 7.7.1 and Vol 1, Pt 6, Ch 6, 7.7 Definitions and details of tests 7.7.2 will be accepted as a leak test on the condition that safe access
to all joints being examined is provided, see
Vol 1, Pt 6, Ch 6, 7.8 Safe access to joints 7.8.1. Where a
hydrostatic or hydropneumatic test is applied as a leak test, the external boundaries
are to be free of any liquid residue prior to the commencement of the test.
7.5.9 Air tests of joints can be conducted at any stage during construction provided that all
work that might affect the tightness of the joint is completed before the test is
carried out.
7.5.10 Where acceptable to the attending Surveyor, provided that careful visual inspections
show a continuous uniform weld profile shape, free from repairs, and the results of
selected NDE testing show no significant defects, the leak testing of automatic butt
welds and semi-automatic (flux core arc welding) butt welds may be omitted.
7.6 Gastight testing
7.6.1 Where
LR has been requested to witness gastight testing in accordance with
a specified standard, the boundaries of citadels and zones defined
in Vol 1, Pt 4, Ch 1, 7 Design guidance for nuclear, biological and chemical defence are to be tested
for gas tightness using a pressure drop test. In addition, compartments
containing noxious or explosive gases such as Acetone, Dope, Flammable
stores, Oxygen, etc. are to be subject to a pressure drop test.
7.6.2 The
test is to be carried out with compartment as near to completion as
possible. Further work on a compartment after the test may result
in a retest.
7.6.3 In certain compartments that are not able to be made fully gastight due to
operational requirements, a greater fall in pressure may be accepted at the discretion
of the surveyor. In no case is the pressure to drop more than 0,0075 bar (75 mm of
fresh water) in 10 minutes from an initial 0,015 bar (150 mm of fresh water).
7.6.4 Consideration
will be given to the testing of adjacent boundaries or equivalent
in those spaces which are not able to be closed, such as gun rings
and main machinery spaces.
7.7 Definitions and details of tests
7.7.1 Hydrostatic test is a test conducted by filling a space with a liquid to a
specified head. Unless another liquid is approved, the hydrostatic test is to
consist of filling a space with either fresh or sea water, whichever is appropriate
for the space being tested, to the level specified in Table 6.7.1 Testing
requirements For
tanks intended to carry cargoes of a higher density than the test liquid, the head
of the liquid is to be specially considered.
7.7.2 Hydropneumatic test is a combination of a hydrostatic test and a
tank air test, consisting of partially filling a tank with water and conducting a
tank air test on the unfilled portion of the tank. A hydropneumatic test, where
approved, is to be such that the test condition in conjunction with the approved
liquid level and air pressure will simulate the actual loading as far as
practicable. The requirements for tank air testing shown in Vol 1, Pt 6, Ch 6, 7.7 Definitions and details of tests 7.7.4 and the safety precautions given in Vol 1, Pt 6, Ch 6, 7.5 Leak testing are
to be adhered to.
7.7.3 Hose test is a test used to verify the tightness of joints with a jet of
water. The jet of water is to be directed perpendicular to the joint. It is to be
carried out with the pressure in the hose nozzle maintained at not less than 2,0 bar
during the test. The hose nozzle is to have a minimum inside diameter of 12 mm and
is to be situated no further than 1,5 m from the joint. Where a hose test is not
practical because of possible damage to machinery, electrical equipment insulation
or outfitting items, it can be replaced by a careful visual examination of welded
connections, supported by an ultrasonic or penetration leak test, or an
equivalent.
7.7.4 Tank air test is to be used to verify the tightness of a compartment by means
of an air pressure differential and leak indicator solution. An efficient indicating
solution (e.g. soapy water) is to be applied to the weld or penetration being tested
and is to be examined whilst an air pressure differential of not less than 0,15 bar
is applied by pumping air into the compartment. Arrangements are to be made to
ensure that any increase in air pressure does not exceed 0,30 bar. A U-tube with a
height sufficient to hold a head of water corresponding to the required test
pressure is to be used for verification and to avoid overpressure. The
cross-sectional area of the U-tube is not to be less than that of the pipe supplying
air to the tank. Alternatively, two calibrated pressure gauges can be considered
acceptable. All boundary welds, including pipe connections in the compartment are to
be examined twice. The first is to be examined immediately upon applying the leak
indication solution; the second approximately five minutes afterwards.
7.7.5 Compressed air fillet weld test. This test consists of compressed air being
injected into one end of a fillet welded joint and the pressure verified at the
other end of the joint by a pressure gauge. Pressure gauges are to be arranged so
that an air pressure of at least 0,15 bar above atmospheric pressure can be verified
at each end of all passages within the portion being tested. A leak indicator
solution is to be applied and the weld line examined for leaks. A compressed air
test can be carried out for partial penetration welds where the root face is greater
than 6 mm.
7.7.6 Vacuum box test is a test used to verify the tightness of joints by means of a
localised air pressure differential and leak indicator solution. The test is to be
conducted with the use of a box with air connections, gauges and an inspection
window that is to be placed over the joint being tested with a leak indicator
solution applied. The air within the box is to be removed by an ejector to create a
vacuum, i.e. a pressure differential of 0,20 to 0,26 bar inside the box.
7.7.7 Penetration test can be used where a hose test is not practical
to assess butt welds, see
Vol 1, Pt 6, Ch 6, 7.7 Definitions and details of tests 7.7.3, by applying a low surface tension liquid to one side of a
compartment boundary. When no liquid is detected on the opposite side of the
boundary after expiration of a defined period of time, the verification of tightness
of the compartment’s boundary may be assumed. A developer solution can be applied on
the other side of the weld to aid leak detection.
7.7.8 Gastight test. The pressure in the compartment is to be brought to 0,015 bar
and the supply isolated. The fall in pressure after 10 minutes is not to be greater
than 0,0013 bar. If the specified pressure drop occurs, the compartment is to be
inspected for leaks and the test repeated until the specified standard is achieved.
A U-tube filled with water to a height corresponding to the test pressure is to be
fitted for verification and to avoid overpressure. The U-tube is to have a
cross-section larger than that of the air supply pipe.
7.7.9 Protective coating. Protective coating is the coating system applied to
protect the structure from corrosion. This excludes the prefabrication primer.
7.8 Safe access to joints
7.8.1 For leak tests, safe access to all joints under examination is to be provided.
|